Yesterday I changed a motherboard on my SQL server 7.0.
Today I noticed that jobs has not been started last night,
and I noticed that date is wrong on this machine,so I did
set the date and time and rebooted the machine, however
still can not see the next run date on scheduled job, even
if I create a new job, I can not see that. Does anyone
know how to fix this?
Thanks in advance-Rob
Hi Rob,
I learned the Job of SQL Server 7.0 did not start after changing the
motherboard and you cannot see the value of "Next run date" property of the
job. As far as I know, after changing the motherboard of the machine,
generally, the old operation system will crash. Do you mean your old
operation system is still available and there is not any problem?
According to your description, it seems all the jobs on your problematic
machine have this problem. If I have misunderstood, please feel free to let
me know. Have you started the SQL Server agent? If the problem still
occurred after starting SQL Server agent, what's the message in the Next
Run Date field of the problematic job?
I am looking forward to hearing from you soon.
Regards,
Michael Shao
Microsoft Online Partner Support
Get Secure! - www.microsoft.com/security
This posting is provided "as is" with no warranties and confers no rights.
|||Hi Rob,
How is the issue going on your side? Do you mean that the "Next Run Date"
column shows "(Date and Time are not available)" value? Even for a newly
created job although it has a valid schedule?
1. Please check again to see if the SQL Server Agent Service is started and
the jobs are enabled.
Right click on one of the jobs -> properties -> schedules tab -> make sure
there is a schedule set up for this job.
If so -> choose the schedule -> edit -> make sure the schedule is enabled
(checkbox is checked)
If not, check it and click ok and apply.
Now, right click on "Jobs" under SQL Server Agent and choose refresh. Check
if the next run date column shows any values. If so, please check each and
every single job to check if the schedule has been enabled.
2. If it still does not help, check in the MSDB database to see if you can
see the date but not in the GUI? Try the following SQL statement.
Select schedule_id, name, next_run_date, next_run_time from sysjobschedules
3. If it also does not show up in MSDB database, please try to run DBCC
CHECKDB against the MSDB database. Also, please enable and provide the SQL
Server Agent log.
For more information regarding SQL Server Agent log, please see the
following article on SQL Server Books Online.
Topic: "SQL Server Agent Properties (General Tab)"
4. If the date shows correctly in the MSDB database, check if an end date
has been specified for the job schedule and if it is already past the end
date?
5. Please run sp_help_job against the jobs to see if the next_run_date and
next_run_time shows correctly?
sp_help_job @.job_name = '<job_name>'
I am looking forward to hearing from you soon.
Regards,
Michael Shao
Microsoft Online Partner Support
Get Secure! - www.microsoft.com/security